GATE - 2006 | OS | The process state transition diagram of an operating system is as given

GATE - 2006 | OS | The process state transition diagram of an operating system is as given
Posted on 18-02-2022

GATE - 2006 [Operating System]

Question:

The process state transition diagram of an operating system is as given below.

The process state transition diagram of an operating system is as given below.

Which of the following must be FALSE about the above operating system?

 

A

It is a multiprogrammed operating system

B

It uses preemptive scheduling

C

It uses non-preemptive scheduling

D

It is a multi-user operating system

   

Solution:

Option B is wrong.

Because given OS is non-prempting scheduling algorithm.

Thank You